Tricon has performed $11,615,000.00 of work over the last seven years with the latest being the Terminal Front Facade complete makeover.

The Front Facade was a two phase project that had a seven month timeline to complete, all while the airport stayed 100% operational.

Maintaining the schedule and communication with the Engineer was essential to plan and coordinate relocation activities with the airlines, all of which required travel from their corporate headquarters in other states to complete the relocations. Although challenges were encountered during the project due to existing site conditions, Tricon was able to maintain the proposed construction schedule and meet the intermediate and final milestones set for the project.

Eric Scott | Project Engineer | Foth